Construction of the Azuma Kofuji solar park began in August 2020, and the first kilowatt hour of clean electricity was fed into the grid at the end of September 2022. Annually, the solar park, which is spread over several sub-areas, will produce around 107 million kilowatt hours of electricity. This corresponds to the average consumption of around 31,000 Japanese households.
Juwi Shizen implemented the project as EPC service provider. With the largest project in the joint venture's history, the project volume implemented since its foundation in 2013 now increases to a total of 602 megawatts. Another 140 megawatts of solar capacity is currently under construction.
Renewable energy plants on abondoned former agricultural land encouraged by law
The completed facility covers an area of approximately 186 acres, most of which is unused farmland. The construction of renewable energy plants on such abandoned former agricultural land is encouraged by law in Japan.
Also interesting: Luxor Solar KK partners with Next2Sun to realize first Agri-PV project in Japan
The solar park is located in Fukushima Prefecture, about 80 kilometers from the Fukushima Daiichi nuclear reactor. There, core meltdowns occurred in several reactor units in March 2011 as a result of an earthquake and a tsunami triggered by it, making it one of the largest nuclear disasters in history. (hcn)