RWE constructs battery storage facility with 235 MWh 

The BESS is scheduled to supply balancing energy to stabilise the electricity grid from second half of 2024. This will entail the plant taking excess power from the electricity grid and feeding it back into the system when required, in order to maintain the required grid frequency. The battery storage facility will also be deployed on the wholesale market. Electricity will be taken into the storage system if electricity prices are low, and conversely will be fed out when prices are high.

Optimization of RWE`s German power station portfolio

The planned battery storage facility can operate at its maximum capacity of 220 MW for over an hour. That is enough to charge the equivalent of about 4,000 EVs. The facility will also be virtually networked with RWE power stations in Germany, which will make it possible to control whether the storage units work alone or in conjunction with other power stations to supply balancing energy. The new battery storage facility thus optimises the use of RWE’s German power station portfolio across a range of technologies. In this regard, RWE benefits from its many years of experience with energy storage systems and is therefore taking care of the detailed planning, modelling, system integration and commissioning of the project directly and entirely on its own.

In Neurath, batteries with a total capacity of 80 MW (84 MWh) will be installed on an area of around 7,500 m², which is the equivalent of about one football pitch. About 50 million euros of the planned total investment volume of 140 million euros will be invested in Neurath.

Batteries with a total capacity of 140 MW (151 MWh) will be installed at Hamm-Uentrop, covering an area of 14,000 m². Hamm will benefit from investment of about 90 million euros of the planned total investment volume of 140 million euros.

Important signal for the region

“As the proportion of renewables in the electricity mix increases, so does the need for flexible battery storage systems. They balance out fluctuations in the electricity grid in seconds, which means they are the key to a reliable electricity supply. In terms of size and technology, the new large-scale battery storage facility in Neurath and Hamm is setting standards throughout Europe“, Roger Miesen, CEO RWE Generation said.

“With this battery storage facility, RWE is providing a major boost to structural transformation in North Rhine-Westphalia. By making practical use of the existing locations and grid connections, we are making the traditional power plant sites of Hamm and Neurath important partners for renewables“, Lars Kulik, member of the Board of RWE Power stated.

“The decision in favour of Neurath is an important signal from RWE to the entire region. So even after the exit from lignite, Neurath will continue to be important in helping to stabilise the grid and ensure a reliable electricity supply“, Klaus Krützen, Mayor of Grevenbroich underlined.

Did you miss that? "Large-scale battery storage indispensable"

“The construction of the large battery storage facility at the Westfalen power plant once again underlines the tradition and importance of Hamm as an energy location. The large-scale battery storage facility secures the energy supply and forms an important foundation for the success of the energy transition. We are pleased that RWE is accompanying us on the way to a climate-neutral economy in Hamm“, Marc Herter, Mayor of Hamm said.

Battery storage investments of RWE

Battery storage systems are an essential part of the energy transition because they store the leftover electricity resulting from overproduction in the grid and make it available again when it is needed. As one of the leaders of the energy transition, RWE develops, builds and operates battery storage systems in Europe, Australia and the US. RWE currently operates a total installed battery storage capacity of approximately 300 MW (380 MWh) and is implementing battery storage projects of more than 900 MW (2,300 MWh) worldwide. Globally, RWE aims to build three gigawatts of batteries by 2030.

Also interesting: RWE: 2.7 GW new-build solar projects

In Germany, RWE commissioned its mega battery in Lingen and Werne, with a total capacity of 117 MW, at the beginning of 2023. It also plans to virtually connect the battery storage system with its run-of-river power plants on the Moselle River. In March, the company acquired British developer JBM Solar, with an advanced development pipeline of 2.3 gigawatts of battery storage projects. Following the commissioning of the Indeland solar farm with its 4.8-MW battery storage facility, RWE is currently constructing further battery storage projects of this nature at the Garzweiler open-cast mine. And RWE recently won an Australian tender for a long-term battery storage facility (50 MW/400 MWh). (hcn)